Uttarkashi tunnel rescue: first day of vertical drilling, 19.2 of 86 metres done

Updated : Nov 27, 2023 18:01
|
PTI

Vertical drilling of 19.2 metres was done on Sunday to create an alternative escape route for the 41 workers trapped inside the collapsed tunnel in Silkyara here for two weeks, an official said.

Drilling to create a vertical pathway from the top of the hill above the collapsed tunnel began on Sunday, a day after an auger machine carrying out horizontal drilling broke down.

Rescuers have to drill down 86 metres from above to reach the trapped workers.

Vertical drilling has gone up to 19.2 metres so far, NHIDCL MD Mahmood Ahmed said at a press briefing in Silkyara on Sunday evening.

Also watch: Plasma cutter to remove auger machine from rubble, tunnel rescue to begin after that: CM Pushkar Dhami

"The exercise is going on smoothly and if it goes like this without facing obstructions, we can hope to finish it in four days by November 30," he said.

On Saturday, the auger machine's blades got stuck inside the rubble, hindering the multi-agency rescue effort that began on November 12 when a portion of the under-construction tunnel on Uttarakhand's Char Dham route collapsed following a landslide, trapping the 41 workers inside. 

Uttarkashi Tunnel Update

Recommended For You

editorji | India

AAP accuses BJP of detaining workers in Gujarat ahead of local polls

editorji | India

Assam records 85.21 pc polling, CM says high voter turnout 'not ordinary but historic'

editorji | India

Will abolish TMC’s mafia Raj weighing heavily on people: PM Modi in Asansol industrial hub

editorji | India

Kharge expresses regret over 'illiterate' remark, says he has highest of respect for Gujaratis

editorji | India

Assam BJP files complaints against Kharge with police, EC over 'hate' speech