Mizoram to get first rail link to Aizawl with Bairabi-Sairang line

Updated : Jul 03, 2025 10:21
|
PTI

To connect Mizoram's capital Aizawl to the railway network, the Northeast Frontier Railway (NFR) sourced construction material and labour force from across the country.

The 52-km Bairabi-Sairang (near Aizawl) rail line, built at a cost of approximately Rs 8,000 crore, is ready and will soon be inaugurated by Prime Minister Narendra Modi.

Vinod Kumar, chief engineer of the project, said his team ordered almost all construction material from other states.

"Crushed stones were brought from Assam, West Bengal and Jharkhand. We purchased sand from Silchar and Guwahati. We sourced reinforcement rods from Kolkata and bent them near the highway as carrying them to the construction site was not possible due to their length. Then, we straightened them for use at the site," he said.

"Small vehicles cannot carry 12-ft-long rods and big vehicles cannot ply on these roads," he added.

According to Kumar, steel girders used for the project were manufactured in Raipur in Chhattisgarh, Kolkata in West Bengal, and Wardha and Ahmednagar in Maharashtra.

NFR officials said that carrying girders to the construction site posed a huge logistical challenge and several special arrangements had to be made.

"There are two approach roads to Guwahati from Aizawl and both often get closed due to landslides or poor conditions. So, we carried the girders up to Bairabi using the rail network and then took them to the site by making special transportation arrangements," Kumar elaborated.

"Cranes were dismantled to take them to the site to place these girders on the bridge. A day's work took more than a month to complete due to all these reasons," he said.

Both skilled and unskilled labourers who worked on the project were from West Bengal, Assam, Uttar Pradesh, Bihar and Jharkhand, he added.

According to the officials, with the completion of the Bairabi-Sairang line, Mizoram will be the fourth northeastern state to have its capital city linked to the national railway network.

According to the NFR, the line has 48 tunnels covering a distance of 12.853 km, 55 major and 87 minor bridges, five road overbridges and nine road underbridges. One of the bridges, numbered 196, stands 104 metres tall -- 42 metres taller than the Qutub Minar.

The railway line was commissioned in four phases -- Bairabi-Hortoki (16.72 km) commissioned in July 2024, Hortoki-Kawnpui (9.71 km), Kawnpui-Mualkhang (12.11 km), and Mualkhang-Sairang (12.84 km), all three commissioned in June this year.

Mizoram

Recommended For You

editorji | India

Messi event stadium rampage: Calcutta HC to hear petitions seeking transfer of probe to central agencies

editorji | India

Why remove Mahatma Gandhi's name, asks Priyanka on move to replace MGNREGA

editorji | India

EAM Jaishankar offers India’s support to Australia after Bondi Beach attack

editorji | India

New opportunity is party's blessing: BJP's national working president Nitin Nabin

editorji | India

Nehru made Kashmir issue controversial, India got extremism, separatism from there: Adityanath