The location for vertical drilling to bring out 41 workers trapped inside the Silkyara tunnel has been identified.

As the rescue operations entered the 11th day, an official said that the road work for vertical drilling on the hill above the tunnel is almost complete.

A piling machine that was stuck yesterday due to the road being narrow, has now reached the tunnel site.

Meanwhile, the horizontal drilling has been resumed and food is being supplied through a six-inch pipe.

According to officials, 800 diameter steel pipes have been inserted up to 32 metres through the rubble so far.

Also Watch: Delhi air quality dips into 'severe' category at many places as AQI crosses 400 again

Uttarkashi tunnel collapse

Recommended For You

editorji | India

AAP accuses BJP of detaining workers in Gujarat ahead of local polls

editorji | India

Assam records 85.21 pc polling, CM says high voter turnout 'not ordinary but historic'

editorji | India

Will abolish TMC’s mafia Raj weighing heavily on people: PM Modi in Asansol industrial hub

editorji | India

Kharge expresses regret over 'illiterate' remark, says he has highest of respect for Gujaratis

editorji | India

Assam BJP files complaints against Kharge with police, EC over 'hate' speech